Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

B.C. Hydro’s Site C set back by COVID-19, foundation changes

Peace River diversion still on track for this fall

B.C. Hydro’s plan to have the third dam on the Peace River complete and in service by 2024 has been set back by work scaling down due to COVID-19 restrictions on construction projects, and additional foundation strengthening for the powerhouse and spillway.

In a progress report filed with the B.C. Utilities Commission July 31, B.C. Hydro CEO Chris O’Riley says the Site C project is still on track to divert the Peace River through a pair of tunnels and begin in-river work. But that too has been complicated by geological conditions. The financial impact of the coronavirus delays and additional work will be better known in the fall, O’Riley said.

“Pandemic-related delays will present further cost pressure on the budget,” O’Riley wrote in a letter to BCUC chair David Morton. “As the evolution of the pandemic is uncertain and the date of resolution is unknown, various cost and scheduled impact scenarios continue to be assessed and refined as part of the re-baselining process.”

The incoming NDP government reluctantly decided to carry on with Site C, after former premier Christy Clark vowed to push the project “past the point of no return” before the 2017 B.C. election. In doing so, Premier John Horgan approved an updated cost estimate of $10.7 billion to complete it, an increase of about $1 billion from the initial estimate.

RELATED: Site C dam project carries on under NDP government

RELATED: NDP pays off $1.1B in B.C. Hydro debt, seeks rate cut

RELATED: After losing at every level, West Moberly sues again

Now the combined effects of COVID-19 and a series of problems have pushed the cost up by an amount not yet known. Those issues included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, and first nations treaty infringement claims and an injunction application.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote.

Before the COVID-19 pandemic, Site C was on track for completion by fall 2023 and full service to the B.C. Hydro grid by 2024.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

U’mista Cultural Centre is closed to the public until further notice, as of Nov. 23, 2020. (Zoe Ducklow photo)
U’mista closed until further notice due to new restrictions

North Island on high alert against COVID-19

Port Hardy Rotary Christmas Float. (North Island Gazette file photo)
Rotary float returns to Port Hardy to spread much needed Christmas cheer

The Christmas Cheer Float is a festively decorated full-size semi-tractor.

Email letters to editor@northislandgazette.com and we will publish online and in print.
LETTER: Fish farms boost North Island economy

“… our local jobs, local taxation revenue, and the like will disappear!”

People wearing face masks to help curb the spread of COVID-19 cross a street in downtown Vancouver, on Sunday, November 22, 2020. The use of masks is mandatory in indoor public and retail spaces in the province. THE CANADIAN PRESS/Darryl Dyck
B.C. reports 17 COVID deaths, 1,933 new cases as hospitalizations surge over the weekend

There are 277 people in hospital, of whom 59 are in ICU or critical care

An aerial shot of Cedar Valley Lodge this past August, LNG Canada’s newest accommodation for workers at the project site in Kitimat. This is where several employees are isolating after a COVID-19 outbreak was declared last Thursday (Nov. 19). (Photo courtesy of LNG Canada)
Forty-one positive COVID-19 cases associated with the LNG Canada site outbreak in Kitimat

Thirty-four of the 41 cases remain active, according to Northern Health

Brenda Schroeder thought she was reading it wrong when she won $100,000 from a Season’s Greetings Scratch & Win. (Courtesy BCLC)
New home on the agenda after scratch ticket win in Saanich

Victoria woman set to share her $100,000 Season’s Greetings lottery win

Workers arrive at the Lynn Valley Care Centre seniors home, in North Vancouver, B.C., on Saturday, March 14, 2020. It was the site of Canada’s first COVID-19 outbreak in a long-term care facility. THE CANADIAN PRESS/Darryl Dyck
Rapid tests ‘not a panacea’ for care homes, Dr. Bonnie Henry says

B.C. lacks capacity for daily tests of thousands of workers

Join Black Press Media and Do Some Good
Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

(Delta Police Department photo)
Cannabis edibles found in Halloween bag lead B.C. police to illegal lab

Delta police arrested a man and a woman while executing a warrant at a residential property Nov. 20

A woman being arrested at a Kelowna Value Village after refusing to wear a mask on Nov. 22.(@Jules50278750/Twitter)
VIDEO: Woman arrested for refusing to wear mask at Kelowna Value Village

RCMP claims the woman was uncooperative with officers, striking them a number of times and screaming

B.C. Liberal MLA Shirley Bond questions NDP government ministers in the B.C. legislature, Feb. 19, 2020. (Hansard TV)
Cabinet veteran Shirley Bond chosen interim leader of B.C. Liberals

28-member opposition prepares for December legislature session

Most Read