B.C. pulls plug on power projects

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20

Wind turbine components await construction at independent power project near Chetwynd in 2008. High construction costs stalled B.C.'s first commercial wind energy project

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20 by the time a review of projects is complete, Energy Minister Bill Bennett said Thursday.

Bennett said the review is part of a broader effort by BC Hydro to meet his instruction to “spend less money,” as he leads an effort to reduce costs across all government operations.

BC Hydro proposed the move, identifying the 20 project proponents that were not meeting their contract obligations due to financing, regulatory or other problems. That non-performance gives BC Hydro legal authority to delay or terminate contracts.

The utility has contracts with 81 operating projects, mostly run-of-river hydroelectric, and another 47 are under construction or seeking permits after receiving purchase contracts.

BC Hydro released its latest draft resource plan last week, which estimates the province has enough electricity supply to meet growing demand for the next 10 years. Bennett said he is skeptical about that forecast, with population growth and industrial demand from new mines and natural gas development in northern B.C., but it gives the utility some breathing room.

“I’m a real fan of the clean energy industry, but obviously we don’t want to be agreeing to buy more power than what we need,” Bennett said.

BC Hydro has been criticized in recent years for running up billions in deferred debt, as it completes major expansion and seismic upgrading of its network of dams. A new power line to northeast B.C. has run over budget, and the NDP opposition has accused the government of forcing BC Hydro to buy private power at inflated rates through contracts running as long as 40 years.

Bennett said he has asked for a detailed analysis of the cost of private power compared to new sources such as the proposed Site C dam on the Peace River or adding turbines to BC Hydro dams on the Columbia River.

B.C.’s Clean Energy Act requires BC Hydro to be self-sufficient in electricity by 2016, based on an average rainfall year to replenish its hydro dams. The requirement is to minimize the import of power generated by burning coal or natural gas.

Just Posted

Vancouver measles outbreak prompts vaccine vigilance on Island

No cases here yet, but Island health authorities push measles vaccinations - and not just for kids

B.C. BUDGET: Surplus $374 million after bailouts of BC Hydro, ICBC

Growth projected stronger in 2020, Finance Minister Carole James says

VIDEO: North Island Peewee Eagles unleash avalanche of goals against Peninsula in semi-final showdown

The two teams squared up on Sunday morning at the Chilton Regional Arena in Port McNeill.

North Island Seniors Housing Foundation takes the next step towards getting Trustee Road land

Seniors rejoice, Port Hardy council is very much in favour of helping… Continue reading

Port Hardy Volleyball club requests funding from Port Hardy council

The sport of Volleyball is alive and well in the North Island,… Continue reading

Students give two thumbs up to no more B.C. student loan interest

Eliminating the loan interest charges could save the average graduate $2,300 over 10 years

Ontario man accused of killing 11-year-old daughter dies in hospital, police say

Roopesh Rajkumar had been hospitalized with what police described as a self-inflicted gunshot wound

Manitoba ‘pauses’ link with ex-B.C. premier Gordon Campbell after allegations

Campbell had been hired to review two major hydro projects

City of Port Alberni cancels tourist train operations for 2019

Steam train to McLean Mill is out of commission for repairs; city wants to re-examine rail costs

Heritage minute features Japanese-Canadian baseball team, internment

The Vancouver Asahi baseball team won various championships across the Pacific Northwest

UPDATE: Woman, off-duty cop in critical condition after stabbing outside B.C. elementary school

The officer was interceding in an alleged assault when he and the woman were stabbed

$10-a-day child care not in 2019 budget, but advocate not irked

Sharon Gregson with the Coalition of Child Care Advocates of B.C. says NDP on track to deliver promise

B.C. Seniors Advocate questions labour shortage in care homes

Are there really no workers, or are care aide wages too low?

B.C. business groups worry about looming economic decline in wake of NDP budget

The party’s second government budget focused on plenty of spending, business advocates say

Most Read