Slope stabilization work continues on the north bank of the Peace River for the Site C dam, September 2017. (B.C. Hydro)

UPDATE: Decision time for John Horgan on Site C dam

Energy Minister Michelle Mungall says delaying it is off the table

Premier John Horgan’s cabinet intends to make a decision on whether to continue building the most expensive construction project in B.C. history by the end of 2017.

The B.C. Utilities Commission released its independent report on the project Wednesday, ordered by Horgan to fulfil a promise he has repeated many times since becoming NDP leader.

The BCUC report questions whether Site C can make its 2024 completion date, and concludes the cost “may” exceed $10 billion. It describes the option of suspending work and restarting it in 2024 as the “least attractive of the three scenarios” set out by the government.

Energy Minister Michelle Mungall said Wednesday the report is technical and requires further study, but one thing that is clear is that delaying Site C is not an option that would protect B.C. Hydro ratepayers from unnecessary rate increases.

In the legislature Wednesday, Peace River South MLA Mike Bernier called on the government to make a decision within a month, to provide certainty to the people working at Site C. Eight years of study done under the B.C. Liberal government, and court decisions saying consultation with affected people was adequate, mean no further delay is needed, Bernier said.

Green Party leader Andrew Weaver said the report “should be viewed as the final nail in the coffin of Site C,” due to potential cost overruns and the B.C. Liberal government’s rush to secure fixed-term electricity supply to liquefied natural gas projects.

“The one issue of concern” is the transfer of the $4 billion cost of scrapping Site C to be added to the provincial debt, Weaver said.

Horgan’s government instructed BCUC to come up with cost estimates for completing the dam, pausing construction for a more thorough review of alternatives and future electricity demand, or stopping it and restoring the project area.

The report estimates the cost of shutting down Site C and remediating the project area to be $1.8 billion, plus the cost of finding alternative energy sources to meet demand, on top of the $2 billion already spent.

“The suspension and restart scenario adds at least an additional $3.6 billion to final costs and is by far the most expensive of the three scenarios,” the report states.

The BCUC panel also concluded that “increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers as the Site C project with an equal or lower unit energy cost.”

Horgan said Tuesday that one more round of consultation with area Indigenous communities will be conducted next by Indigenous Relations Minister Scott Fraser, and then cabinet will consider its options.

B.C. Hydro has already awarded the major contracts for the powerhouse, river diversion and main civil works in the riverbed.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Forest industry supporters and convoy arrive at B.C. legislature

Rally delivers petition in favour of ‘working forests’

Port McNeill council tackles the issue of AirBnBs

Council wants a public hearing to identify options for short-term rentals in Port McNeill.

Port McNeill council roundup: Feb. 11 meeting

Various stories from Port McNeill council’s Feb. 11 meeting.

Forestry workers vote for new agreement, ending 8-month strike on Vancouver Island

Wage increases, higher premiums and contract language part of new agreement

REVIEW: Poetry helps Conshinz heal from brain trauma

The Book of 1000 Poems, Volumes 1-4, by Conshinz, a.k.a. Port Alice… Continue reading

Protesters barricade Premier John Horgan’s home ahead of B.C. budget unveiling

Demonstrators from the Extinction Rebellion have blocked the Langford driveway

Budget 2020: B.C. adds tax to sweet drinks and sodas

All soda, vending machine drinks will be subject to higher PST

Budget 2020: B.C. unveils new grant for students, phases out debt-relief program

For the first time, diploma, certificate students qualify for yearly post-secondary grant

2020 Budget: ICBC shortfall continues ahead of new rate-reduction plan

ICBC operating with $91-million deficit for 2019-2020 fiscal year

Budget 2020: B.C. NDP taps top tax bracket for more revenue

Minimum wage set to pass $15 an hour by 2021

Budget 2020: Not much new for B.C.’s struggling forest industry

Focus on wood waste utilization, efficiency, ministry budget cut

Skull reconstruction gives new insight into unknown man found in B.C. cemetery

RCMP released a 3-D skull reconstruction of a man who was found dead on July 2, 1998

Ten poisoned eagles rushed to veterinary hospital in Nanaimo

Eagles stricken after eating flesh of euthanized animal at Nanaimo Regional Landfill

Trudeau says Wet’suwet’en crisis, rail blockades a critical moment for country

First Nations leaders suggest it may be time to peacefully end the blockades

Most Read