Trans Mountain pipeline expansion work near Jasper Alberta

Long list of conditions for Trans Mountain approval

Kinder Morgan says 145 conditions on wildlife, ocean impact, earthquake and other hazards is "rigorous but achievable"

The National Energy Board has released a draft list of 145 conditions for approval of Kinder Morgan Canada’s oil pipeline expansion project, including environmental protection plans for land and marine operations.

Conditions include the possibility of dredging for the expansion of the Westridge Marine Terminal in Burnaby, where the original Trans Mountain pipeline has delivered crude oil and refined products since 1953.

Kinder Morgan is proposing to twin the line to ramp up shipments of diluted bitumen from northern Alberta that began intermittently in the late 1980s. The $5.4 billion expansion project would nearly triple the line’s capacity to 890,000 barrels per day, resulting in a seven-fold increase in oil tankers entering and leaving Vancouver harbour.

Kinder Morgan Canada president Ian Anderson said Thursday the company will be seeking clarification on the timing of some of the conditions, and will file its comments to the NEB review panel Aug. 20. Most major conditions, including plans for watercourse crossings along the route, are to be filed at least 90 days before construction begins.

“Our initial review of the draft conditions is that they are rigorous but achievable,” Anderson said.

NEB hearings are to resume Aug. 24, where the B.C. government is expected to formalize its position, based on Premier Christy Clark’s five conditions for new heavy oil pipelines. They include a “world-class” spill response capability on land and sea, approval and benefit sharing by affected First Nations, and a still-undefined “fair share” of benefits for the province.

Those conditions were included in B.C.’s position opposing the Enbridge Northern Gateway project, which the federal government approved with its own list of more than 200 conditions. The province does not have authority to veto either pipeline project, as each would run from Alberta to B.C.

Draft conditions for Trans Mountain include identification of all sites on the proposed second line affected by earthquake, including the “Holocene for Sumas Fault, Vedder Mountain Fault, Fraser River-Straight Creek Fault and Rocky Mountain Trench, as well as other possible hidden faults.”

Conditions also include submitting records of landowner consultation on the route, and a plan for aboriginal participation in monitoring construction.

 

Just Posted

North Island College holding information session on new culinary diploma

Get a sneak peek at the new culinary kitchen at the Campbell River campus

Council approves replacement of overhead heaters at Fire Hall

Port Hardy council has agreed to spend $11,000 on the replacement of… Continue reading

North Island Eagles minor rep hockey organization hand out year-end awards in Port McNeill

It was quite the season and then some for minor rep hockey here in the North Island.

North Island resident to campaign on climate, economy for Liberal Party seat in Ottawa

Peter Schwarzhoff joins race for the second time in North Island-Powell River riding

Press release: Port Alice Health Centre service model announced

“a sustainable and dependable model of health care service delivery in Port Alice is a priority”

Kelowna toddler suffers cracked skull after fall from balcony

Neighbour who found the two-year-old boy said he has a bump the size of a golf ball on his head

Crews fight fire with fire to keep blaze from northern Alberta town

The wildfire now covers some 920 square kilometres

Man in B.C. charged with murder and arson in 2016 New Brunswick death

He is charged in the death of 71-year-old Lucille Maltais, who was found inside a burned down home

Improve your life and theirs, adopt a cat from the BC SPCA

The BC SPCA holds an adult cat adoption promotion

Support growing for orphaned Okanagan child after father dies in highway crash

Family thanks emergency crews for assistance in traumatic incident

RCMP probe if teen was intentionally hit with ski pole by mystery skier on B.C. mountain

The incident happened on March 20 on Grouse Mountain. Police are urging witnesses to come forward

Pipeline protester chimes in on Justin Trudeau’s B.C. fundraising speech

The government purchased the Trans Mountain pipeline and expansion project for $4.5 billion