Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

VIDEO: North Island Peewee Eagles unleash avalanche of goals against Peninsula in semi-final showdown

The two teams squared up on Sunday morning at the Chilton Regional Arena in Port McNeill.

North Island Seniors Housing Foundation takes the next step towards getting Trustee Road land

Seniors rejoice, Port Hardy council is very much in favour of helping… Continue reading

Port Hardy Volleyball club requests funding from Port Hardy council

The sport of Volleyball is alive and well in the North Island,… Continue reading

Should aquaculture programs be offered at North Island College in Port Hardy?

“I think it would be very timely to have an aquaculture program”

Island Health issues press release regarding Port Alice Health Centre service changes

Island Health will be hosting a community meeting in Port Alice Feb. 20 at 6 p.m. in the rec centre.

Trudeau’s principal secretary, Gerald Butts, resigns amid SNC-Lavalin furor

Butts categorically denies the accusation that he or anyone else in the PMO improperly pressured former attorney general Jody Wilson-Raybould

Lost a ring? This B.C. man will find it for you

Chris Turner founded The Ring Finders, an international directory of metal detector hobbyists

Poverty coalition has high hopes for B.C. poverty reduction strategy

Funding allocation expected to be released with 2019 budget

‘How did we get here?’: B.C. mom of transplant recipient worries about measles outbreaks

Addison, 7, cannot get a live vaccine because she has a heart transplant

Steelhead LNG stops work on Kwispaa LNG project near Bamfield

Huu-ay-aht First Nations ‘deeply disappointed; Steelhead says funding is the problem

NDP Leader Jagmeet Singh calls for public inquiry over SNC-Lavalin questions

Vancouver member of Parliament Jody Wilson-Raybould resigned from cabinet last week

Canadian airlines waiting for guidance from Ottawa over X gender option

Major U.S. airlines said they will change their process so passengers can identify themselves along non-binary lines

Moose Hide campaign takes message to Canadian schools

Campaign launches new K-12 education platform

‘Violent’ B.C. man wanted on Canada-wide warrant

Prince George man with ties to Vernon sought by police

Most Read