Artist’s rendering of the Site C dam, the third hydro dam on the Peace River that started construction in 2015. (BC Hydro)

$1.6B contract one of three awarded for Site C dam in northeastern B.C.

Government says as many as 1,600 workers by the peak of construction in 2021 will be hired

A $1.6 billion contract has been awarded for construction of the Site C hydroelectric dam in northeastern British Columbia, just three months after the province’s NDP government reluctantly allowed the megaproject to continue.

BC Hydro says the contract has been awarded to Aecon-Flatiron-Dragados-EBC Partnership to build the dam’s generating station and spillways, with work beginning this spring.

The Crown corporation overseeing the development near Fort St. John says the contract for the powerhouse, penstocks, spillways and power intakes involves pouring the equivalent of 280 Olympic-sized swimming pools of concrete, as well as installation of enough rebar to build nearly five Eiffel towers.

The utility says the two spillways alone are 17-storeys high and five highway-lanes wide, making the contract the project’s second-largest, just under the $1.75 billion contract inked in 2015 with Peace River Hydro Partners for the dam’s foundation and other civil works.

Two separate contracts, worth a total of $56 million, have gone to a Nanaimo-based company for construction of the Site C substation and to a Quebec-based firm that will supply the bridge and gantry cranes for the generating station and spillways powerhouse.

READ MORE: Site C dam goes ahead, cost estimate now up to $10.7 billion

READ MORE: Environmental groups slam NDP decision to continue with Site C

Hydro says in a news release that the partnership awarded the $1.6 billion contract expects to hire as many as 1,600 workers by the peak of construction in 2021 and has agreed to give priority to Indigenous applicants and those from northeastern B.C.

Premier John Horgan’s government announced in December that it had no alternative but to complete Site C rather than absorb the $4 billion cost of scrapping it.

At the time, Agriculture Minister Lana Popham said in a Facebook post that the approval was the most difficult decision of her career and she was ”grieving the loss of agricultural land in the flood zone of Site C.”

The dam, the third across the Peace River, will flood an 83-kilometre stretch of valley west of Fort St. John.

It was originally estimated to cost $8.3 billion, but Friday’s contract announcement from Hydro projects a revised budget of $10.7 billion.

When complete, BC Hydro estimates Site C will provide enough power to heat and light as many as 450,000 homes a year.

The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

Port Hardy’s RCMP Staff Sgt. Wes Olsen: ‘It’s business as usual’ after cannabis legalization

Local RCMP will still be on the lookout for impaired driving despite cannabis legalization.

Jay Dixon finishes top three for School and District Leadership award

“I believe it’s all of our responsibility for our schools to provide quality education,” said Dixon.

7 Mile Landfill operations tender closes October

Taxes covering the landfill have not increased over the past 15 years and are not expected to soon.

VIDEO: This is what buying legal pot in B.C. looks like

Take a look inside B.C.’s first and only legal pot shop located in Kamloops

10 things still illegal in the new age of recreational cannabis

Pot is legal – but there are still a lot of rules, and breaking some could leave you in jail

B.C. NDP retreats again on empty-home tax for urban areas

Rate reduced for all Canadians, dissident mayors to get annual meeting

Two B.C. cannabis dispensaries raided on legalization day

Port Alberni dispensaries ticketed for “unlawful sale” of cannabis

Canada not sending anyone to Saudi business summit

Sources insist Ottawa never intended to dispatch a delegation this time around

VPD ordered to co-operate with B.C. police watchdog probe

According to the IIO, a court is ordering Vancouver police to co-operate with an investigation into a fatal shooting

Port Hardy municipal candidate Rick Marcotte’s profile

“I feel that we have had a wonderful council that can discuss issues of importance,” said Marcotte.

Earthquake early-warning sensors installed off coast of B.C.

The first-of-its kind warning sensors are developed by Ocean Networks Canada

Port Hardy municipal election candidate Leightan Wishart’s profile

Wishart speaks on his experience: “I’ve was elected to the School Board in 2002.”

Port Alice municipal election candidate Doug Worthington’s profile

“We must take advantage of provincial and federal grants whenever possible,” Worthington said.

Port McNeill municipal election candidate Falyn Lynch’s profile

“It’s time for progress, fresh ideas, renewed energy,” Lynch said.

Most Read