Anti-smart meter protester Sharon Noble greets delegates at B.C.'s 2012 municipal convention in downtown Vancouver. Wireless meters have been blamed for bee deaths

B.C. smart meters cleared in Ontario debacle

$1 billion over budget, Ontario tried to use smart grid to shift load to off-peak hours. It hasn't worked

Ontario has become notorious for bad energy policy decisions, from leaky nuclear plants and brownouts, to a costly green energy subsidy deal with Samsung, to a pair of hastily cancelled gas-fired power plants that helped push former premier Dalton McGuinty from office.

So it was no surprise to weary Ontario electricity ratepayers when Auditor General Bonnie Lysyk wrapped up 2014 with a report condemning the province’s wireless smart meter program for a $1 billion cost overrun and failure to reach the program’s goal of reducing power consumption.

Unlike BC Hydro’s wireless meter program, Ontario used the smart grid’s real-time consumption data to offer discounts for off-peak power consumption, hoping to ease the load on its outdated power grid while giving customers some relief from soaring rates. But few embraced the incentive to run their clothes dryers late at night to save money.

Diehard smart meter opponents in B.C. jumped at the bad news from Ontario. Their theories of sudden billing surges, vague health concerns and even smart meter surveillance have all been debunked, but here they had a credible voice saying they are a waste of money.

Alas for them, Lysyk held up B.C.’s smart meter program as the model Ontario should have followed.

The Ontario government “did not complete any cost-benefit analysis or business case prior to making the decision to mandate the installation of smart meters,” the auditor wrote. “This is in contrast to other jurisdictions, including British Columbia, Germany, Britain and Australia, all of which assessed the cost-effectiveness and feasibility of their smart metering programs.”

Lysyk’s report also noted BC Hydro developed its business case in 2006, updated it in 2010 as meter technology evolved, and implemented it in 2011 with a plan to recover costs over 20 years. BC Hydro’s savings come mainly from reduced electricity theft, faster location of power outages and more accurate load management.

B.C. also responded to the anti-smart meter holdouts with an optional fee to cover manual meter readings for those who insisted the cellphone-like data transmissions are a threat to their health.

 

Just Posted

Pregnancy Outreach Program launches in Port Hardy

North Island Building Blocks Program is called K’wi’Kwalayu or “our reason for living”

Find out what the tax increase will be in your area of the Tri-Port

The Gazette reached out to all three communities financial departments requesting numbers to crunch

Tree falls inches away from Port Hardy home

The tree narrowly missed the residence on Wolleson Street

Port Hardy firefighters to earn money for calls

Council has approved a Fire Department Remuneration policy

A memorial mural will be painted in Port Hardy

The mural will honour lives lost to substance abuse and mental health

Trans Mountain pipeline: Is it worth the risk?

Concerns range from the threat of an oil spill to the impact of tanker traffic on wildlife

Loggers Golf Tournament nearly full, sign up to play before June 1

Applewood Ford will be donating a car if a golfer gets a hole in one on the 11th hole.

B.C. to spend $181M to create 200 general practitioner jobs

Jobs will go to new medical school graduates

Federal leaders trade barbs about India trip at press gallery dinner

Justin Trudeau’s infamous trip to India earlier this year was the focus of many of the jabs

B.C. VIEWS: Our poverty reduction plan is already in place

NDP has another promise it needs to appear to keep

WestJet pilot strike averted as parties agree to mediation

Pilots had warned they could go on strike starting May 19

Most Read