An artist’s rendering of the Site C dam, the third hydro dam on the Peace River. BC Hydro image

Site C dam project plagued by problems: expert

E. Harvey Elwin expresses concern about internal BC Hydro and government documents

The mammoth Site C hydro-electric project is seriously behind schedule, plagued by quality problems and marked by secrecy, says an assessment by an international dam expert.

E. Harvey Elwin – hired by a First Nation asking for a court injunction to aspects of the dam’s construction – expresses concern about work at the job site in his 196-page report citing internal BC Hydro and government documents, many of them previously confidential.

“In my opinion, it is the sign of a large performance problem with the (main) contractor meeting the requirements of the specifications and quality of work,” he wrote in the report filed Wednesday in B.C. Supreme Court.

In a letter accompanying a progress report to the B.C. Utilities Commission dated July 11, BC Hydro president Chris O’Riley said the project remains “on time and within budget.”

Spokespeople for the provincial government and contractor Peace River Hydro Partners did not immediately respond to requests for comment.

Elwin, who has worked on dams around the world including China’s Three Gorges project, concludes the dam’s construction is likely to take years longer than BC Hydro says.

READ MORE: Anti-Site C petition approved

The 1,100-megawatt dam and generating station on the Peace River in northern B.C. would flood parts of the traditional territory of the West Moberly and Prophet River First Nations.

In January they filed a civil court case, alleging their rights have been violated.

West Moberly also applied for an injunction to halt construction pending the outcome of the rights case. That motion goes to court Monday. Elwin’s report was filed in support of West Moberly’s case.

BC Hydro has argued any injunction would create heavy budget overruns. It says a two-year injunction would cost an extra $660 million and a three-year stoppage would cost $1.1 billion.

Based on documents BC Hydro was forced to release as part of the court process, Elwin disagrees.

He found that stopping work in 13 areas the West Moberly are most concerned about would delay completion of major milestones by a few months at most. He concluded the cost of a three-year injunction would be $71 million.

Elwin expresses serious concern at the number of reports detailing construction problems.

“I have observed that there are always a large number of (non-conformance reports) generated and being processed. It is also evident that many are not closed rapidly,” he writes. “The number, frequency, and lengths of time to close (such reports) are an indicator of the quality of work.”

Projections for placing concrete are “overly optimistic and not realistically achievable,” he says.

Last year, Elwin says contractors placed 35 per cent of the concrete they were supposed to for a major section of the dam. At that rate, Site C will take well over a decade to finish, significantly past its 2024 completion date, Elwin suggests.

O’Riley’s letter acknowledges the project has had problems meeting its construction schedule. It has also had safety concerns.

He said an agreement has been reached with the main contractor that will accelerate some activities and provide incentive payments to meet deadlines. That’s projected to cost up to $325 million.

“While the agreement will draw on our contingency budget … we have been able to manage the costs within the existing construction budget,” O’Riley wrote.

Elwin is skeptical.

“I seriously doubt the capability of the (main) contractor to take on and effectively perform to an accelerated schedule,” says his report.

The Canadian Press

Like us on Facebook and follow us on Twitter

Just Posted

Port Hardy Fire Rescue looking to replace old equipment

PHFR recently requested funding from the district for new SCBA equipment, citing a $35,000 cost.

Port Hardy council has sent a second cannabis application to LCRB for consideration

Port Hardy council voted in favour to have a cannabis application moved forward to LCRB.

Port Hardy water, sewer and garbage rates may go up

Water rates would increase by 2 per cent, garbage by 2.5 per cent, and sewer by 4 per cent.

VIDEO: North Island female minor hockey jamboree a big success story

“Success is measured by the smiles on the players’ faces, not by the scoreboard.”

FOLLOW-UP: Shelley Downey speaks on her Conservative candidacy

“I anticipate requesting a leave of absence from Port McNeill council,” Downey said.

Story of the Year: Deadly Humboldt Broncos bus crash

The Canadian Press annual survey of newsrooms across the country saw 53 out of 129 editors cast their votes for the Humboldt Broncos bus crash.

VIDEO: Tornado rips through city west of Seattle

Reports indicate five to seven homes damaged in Port Orchard, Wash.

Trial date postponed for man charged with killing Abbotsford police officer

Oscar Arfmann’s trial pushed back from January to May 2019

Privacy watchdog says legal cannabis buyers should use cash, not credit

Some countries could bar entry to individuals if they know they have purchased cannabis

‘A start:’ Alberta critical of Ottawa’s $1.6B package for ailing energy sector

A further $150 million is to be used for clean growth and infrastructure projects

New B.C. Lions coach DeVone Claybrooks adds eight to coaching staff

DeVone Claybrooks has filled out his staff for the 2019 season

Two-year-old attacked by cougar near Mission, B.C.

Boy not seriously injured in incident on Monday afternoon

Trump signs order to create US Space Command

President Donald Trump signs an executive order to create a U.S. Space Command.

Groups preparing new pipeline legal challenge, argue government’s mind made up

A Vancouver-based environment charity is readying itself to go back to court if the federal government reapproves the Trans Mountain pipeline expansion.

Most Read