Let the water flow: BC Hydro to flood John Hart generating station tunnels later this month

The John Hart Generating Station replacement project will soon turn on the taps and fill up the underground tunnels of the new underground hydroelectric generating facility on the Campbell River.

“It’s all culminating with this amazing ability for having waterflow starting this year,” said BC Hydro spokesperson Stephen Watson during a tour of the facility last week. “We’re going to have the water flowing into the tunnels end of March .”

That will be followed by two large water release valves taking over the flow of water into the Elk Falls canyon. Presently, the water is released through gates in the John Hart Dam. Two large water release valves will provide the water flow down Elk Falls Canyon.

The John Hart Generation Station replacement project is a $1.093 billion project replacing the 70-year-old John Hart Generating Station – which exists on the surface at the entrance to Elk Falls Canyon on the Campbell River – with a fully-underground facility built into the bedrock.

Water will actually be running through the tunnels by May and the first of the new turbines will be operating by June with the entire facility up and running by October. The project was initiated in 2007 and construction began in 2014.

“I’ve been fortunate enough to be involved in the project since it started in 2007. It’s been almost 11, 12 years in the making, when it’s all been said and done, and to see it happening like this, the challenges that the contractor has done a great job to overcome, it’s just a really exciting time for this community.”

Once completed, Watson said BC Hydro attains a facility that fulfills three goals: it’s seismically strong, embedded in bedrock; it protects downstream fish habitat by maintaining constant flows because of a bypass facility just to keep those flows going; and the power utility has a new generating facility that will last another 70 years.

“It’s extraordinarily impressive what’s been happening here for the last four years,” North Island MLA Claire Trevena said. “We’ve seen exponential growth from nothing through to a massive cavern to now where we have turbines in place, we have all the valves ready to go we’ve got the work completing.

“It’s been an extraordinary project.”

While turning on the taps is a nice metaphor, it’s not actually that simple. The process is done in stages (see diagram below):

Step 1: The water intake and valves:

  • First, water from the new intake at the dam will fill the water intake structure.
  • Second, with water from the intake structure, the two water release valves that will provide the water flow down Elk Falls Canyon will be commissioned.

Step 2: Tailrace and power tunnel:

  • To add water in tailrace tunnel, BC Hydro will pull the metal stop logs at the tunnel outlet and slowly allow water to enter the tunnel. This may take a day.
  • To fill the power tunnel, the large operating gate within the water intake structure will be opened in stages. There are seven steps for watering up the power tunnel and it may take two weeks to complete.

Step 3: Start commissioning/wet testing:

  • Once all the water is in, Hydro will begin preparing for operation of the generators and water bypass facility.

Source: John Hart Generating Station Replacement Project Feburary 2018 Community Construction Update Report #56.

 

InPower BC CEO Paul Sawyer (left) discusses the water release valves with North Island MLA CLaire Trevena. The John Hart Dam is the concrete structure to the right. Photo by Alistair Taylor/Campbell River Mirror

Just Posted

VIDEO: North Island Bantam Eagles still undefeated, dominate Oceanside Generals in Port Hardy

Who can stop the North Island Bantam Eagles? The answer so far this season is, well, no one.

VIDEO: North Island Atom Eagles tie Victoria Ice Hawks, fall in rematch

The North Island Atom Eagles will be back in league play action at home in January.

Strong winds expected to hit north, west Vancouver Island: Environment Canada

Environment Canada said southeast winds will reach speeds of 70 to 90 kilometres per hour

Town of Port McNeill hesitates on replacing harbour’s dock and ramp

“The danger is the longer we hold on to awarding the bid, the closer we get to the tourist season”

It’s the last day to vote in B.C.’s referendum on electoral reform

Ballots must now be dropped off in person to meet the deadline of 4:30 p.m.

Lawyer for Chinese exec detained by Canada says it’s ‘inconceivable’ she would flee

Meng Wanzhou was detained at the request of the U.S. during a layover at the Vancouver airport

Federal government plans examination of coerced sterilization

The Liberals have been pressed for a rapid response to recent reports on the sterilizations

Huitema, Cornelius named 2018 Canadian Youth International Players of the Year

Huitema was captain of Canada’s fourth-place team at this year’s FIFA U-17 Women’s World Cup

Canada not slowing emissions from oil and gas: environmental groups

New report released at the United Nations climate talks in Poland

Liberal Party moves Trudeau fundraiser from military base

The fundraiser is scheduled for Dec. 19, with tickets costing up to $400

Pipeline protesters arrested at B.C. university

Three protesters were arrested after TRU property allegedly vandalized with red paint

Goodale to ‘examine’ transfer of Rafferty to medium-security prison

Michael Rafferty was sentenced to life in prison in 2012 in the kidnapping, sexual assault and first-degree murder of Tori Stafford

‘Abhorrent’ condition of autistic B.C. boy shows flaws in care system: report

‘Charlie’ was underweight and ‘covered in feces’ when he was removed from his mom’s care

Minister appoints former CIRB chair to resolve Canada Post labour dispute

Postal workers engaged in weeks of rotating walkouts

Most Read